WestHillsConstruction

image description

Case Studies: A Closer Look

Client: Nestle

Posted by in, on June 08, 2013.

Installation of a turn-key Fuel Cell - Energy Storage System.


25 Year Electric Savings over $33,000,000

25 Year Electric Savings: $33,980,121.44

Installation of a turn-key Fuel Cell - Energy Storage System, leveraging two (2) 400kW Fuel Cells and 2MWh of Energy Storage.

Product: UTC 400kW Fuel Cell x 2
Total Output: 800kW AC
Install Cost:  $6,963,135.54
SGIP Rebate:  $2,376,000

FITC: $2,050,534.03

Fed & State Depreciation: $2,977,563.04
Net Cost: $(87,401.36)

25 Year Cash Flow Summary: $30,708,119.64
Time to Payback: 2.63 Years

10 Year IRR: 53.87%
25 Year IRR: 55.45%